Commencement Date: January 11, 2018
Completion Date: May 28, 2018
Scope of Work: The project includes overall design and construction of the entire process, such as scheme design, adjustment of drawings, construction drawing design, construction preparation, construction phase, acceptance phase, and defect liability period. It involves the construction of scenic beauty and landscape lighting at ten points along the approximately 3.8km cruise route on the lakeside of Huayang Lake, the construction of a 1000 square meter performance platform, laying approximately 5300 meters of main and branch lines for electricity, and municipal cable trench works, as well as approximately 200 square meters of dance room renovation works for night cruise supporting facilities. The project encompasses scheme design, scheme adjustment, construction drawing design, equipment supply, installation and commissioning, civil construction, completion acceptance, delivery and use, and provision of other related services.